Installation of wall panels
1 Measurement
Measure dimensions (length, width, height) on site, and draw basic drawings by hand.
2 Drawing Drawings
According to the actual measurement size, through the design software to make plans and construction drawings, calculate the corresponding needs of the square number of wall panels, the number of decorative lines and related supporting facilities.
3 Wall panels of different materials are installed
There may be some differences in the installation of different materials, but basically follow these four sequences, that is, the first board after the line, from the outside to the inside, from the bottom to the top of the back wall.
Board first and line later
Refers to the installation of the main plate, and then the installation of lines. First large area installation and then Angle, edge and other details are processed.
From the outside in
Refers to the sequence of installation from the wall at the entrance of the room to the inside. Because the installation to the back part needs to be cut, it is more beautiful to install from the outside in.
V from the bottom up
It means installing the wall panels from the bottom up,
Back wall first
It refers to the installation of the ceiling before the installation of the wall. When installing the ceiling, fix the keel first. When installing the first wall panel on the wall, fix it on the wall with steel nails first.